CPK AS A COSTING TOOL

Determine current CP or CPK values, then determine fall out rate (0.27% at CPK of 1.0)

Determine average cost of defect.

Estimate production rate for this year

Estimate annual cost of defects:

(production rate X fallout rate X cost/defect

Estimate cost to make improvement

Implimentation Costs

Operating Costs

Estimate CP or CPK after improvement

Determine with PDCA (Plan Do Check Act) Pilot Test

or

Resort to WAG/SWAG/ROMWAG - Wild Ass Guess, Scientific Wild Ass Guess, Rough Order of Magnitude Wild Ass Guess

Use benefit cost ratios to select projects. Return on Investment or Rate of Return or Payback Time.

Management by Fact: Team must be specific in selecting problems and solutions.

It requires data collection and estimates to develop ratios.

"You can get anything you want, if you just help other people get what they want in the process."

Establish purpose, goal, problem to solve

Define the process

Collect data

Convert data to information

Convert information to knowledge

Convert knowledge to ACTION