Vedeler Observatory
Construction History
Official construction started: 1/23/99
Construction finished: 3/27/99
Total
Materials Cost: $2800.
Estimated time for labor: 110 hours
Click on any image for a detailed picture.
CAD drawings West
elevation plan |
|
|
|
|
|
|
2/14/99:
Poured footers for roll off roof support structure. |
2/15/99:
Installed posts for the roll off
roof support structure. |
|
2/20/99: Built roof tracks. Sanded and painted angle iron. |
2/21/99: Finished
roll off roof support structure. |
|
2/23/99:
Painted pier coupling black. |
2/28/99:
Installed all the siding. |
|
3/6/99: Installed
roof shingles. |
3/7/99: Started
painting interior dark blue. |
|
3/13/99: Finished
Electrical. |
3/14/99: Painted
exterior. |
|
3/20/99: Installed
garage door opener for roll off roof. |
3/21/99: Finished
painting exterior. |
| Post Construction Modifications: 5/30/99: Installed powered attic ventilation fan due to excessive heat buildup inside.
|
|